Utility Location project in effect February 16 - February 27

The location project will last 10 days.
Utility location map page 2.

Utility location map page 2.

Utility location effort will cause partial lane closures throughout campus from February 16 through February 27. The attached logistics plan outlines the schedule. Parking & Transportation will reroute busses accordingly based on the day and closure and the contractor will handle all other traffic control. The proposed plan is as follows pending weather:

  • Closure #1 – 2/16/23 – 1 day (10 Hours) starting 7am
  • Closure #2 – 2/17/23 – 1 day (10 Hours) starting 7am
  • Closure #3 – 2/18/23 – 1 day (10 Hours) starting 7am
  • Closure #4 – 2/20/23 – 1 day (10 Hours) starting 7am
  • Closure #5 (Curran) 2/21/23 – 1 day (10 Hours) starting 7am
  • Closure #5a (Turner) – 2/22 - 2/23/23 – 2 days (10 Hours each) starting 7am
  • Closure #6 – 2/24/23 – 1 day (10 Hours) starting 7am
  • Closure #7 – 2/25/23 – 1 day (10 Hours) starting 7am
  • Closure #8 – 2/27/23 – 1 day (10 Hours) starting 7am

 

Additional Images